All exterior windows and doors are in. Roof is on. Plumbing and electrical rough-in will be completed next week. Then interior wall insulation for sound and then drywall.
Thursday, September 12, 2013
Wednesday, July 31, 2013
Thursday, July 18, 2013
Exterior Walls
In less than 4 days the exterior walls of the house were delivered and installed.
Time lapse of the SIPs delivery and wall install.
Kitchen windows.
Andrew, Lauren, and Avery in Andrew's room.
Saturday, July 13, 2013
Concrete Slab
The day started early with the pump truck arriving at 5:30 AM. The first of four concrete trucks showed up around 6:00 AM.
Adding the color that Lauren chose. (In actuality, she just happened to choose the same color that we had already selected, but she loves saying that she chose the color for our floors, so we'll give her those bragging rights.)
Pumping the concrete.
Power troweling the slab.
Time lapse video of the whole day.
Monday, July 1, 2013
Friday, June 21, 2013
Rainy Day
Despite a very drizzly, Pacific Northwest day, the crew got a lot of (wet! heavy!) dirt and sand moved and leveled yesterday. Plumbing will be roughed in early next week, then electrical, and then we'll be ready to pour the slab. Watch for William, our quality control duck, toward the end.